# Road work in Holland, Hudsonville, Coopersville and Saugatuck: November 2 to 8
- URL: https://www.mosaicwestmichigan.com/road-work-holland-hudsonville-november-2-8-2026/
- Published: 2026-11-02T12:30:00.000Z
- Updated: 2026-11-02T12:30:00.000Z
- Description: East 8th Street in Holland stays closed through Thursday, BPW's estimate, and 112th Avenue in Olive Township through late November. The 48th Avenue and Baldwin Street roundabout is marked completed. I-96 near Coopersville keeps a lane closure through November 14. Closures and lane work, by town.
- Author: Mosaic Staff
- Tags: Civic, #roads, Holland, Tri-Cities, Hudsonville-Jenison, Allendale-Coopersville, Lakeshore Allegan, Ottawa County, Allegan County

[Leer en español →](https://www.mosaicwestmichigan.com/obras-viales-holland-hudsonville-noviembre-2-8-2026/)

No new closures were identified in the sources reviewed for this week, and two of the biggest have scheduled completion dates this week. East 8th Street in Holland stays closed between US-31 and Waverly Road for the Board of Public Works water main through Thursday, November 5, BPW's estimate for completing the whole project. 96th Avenue south of Stanton Street, on the Olive and Blendon township line, is scheduled to stay closed through Monday, November 2 for a culvert replacement, with a posted detour by Fillmore Street, 76th Avenue and Taylor Street.

The long one is 112th Avenue between Port Sheldon Street and New Holland Street in Olive Township, including the 112th Avenue and Van Buren Street intersection, closed since Thursday, October 29 for a City of Wyoming water transmission line. The project list shows it closed through November 20; the notice says late November. The posted detour is New Holland Street, 120th Avenue and Port Sheldon Street.

Near Hudsonville, the Road Commission's project list now marks the 48th Avenue and Baldwin Street roundabout as completed, along with the 48th Avenue water transmission main, both Baldwin Street resurfacing jobs and New Holland Street. The left lane of I-96 near Coopersville and Allendale stays closed through November 14\. The project list still shows 172nd Avenue in Grand Haven Township and 96th Avenue north of Blair Street closed, both with end dates that have passed; their current status could not be confirmed. MDOT listed no short-term lane closures in the area when Mi Drive was checked Sunday night.

Here are the road closures, lane restrictions and upcoming projects that the road commissions, MDOT, the City of Holland and the Holland Board of Public Works have posted for Monday, November 2 through Sunday, November 8, grouped by town.

## Holland and Holland Township

### City of Holland

- Closed**E 8th Street, US-31 to Waverly Road**  
Closed for the Holland BPW water main replacement, with traffic control in place through Thursday, November 5, BPW's estimate for completing the whole project. The stretch between Waverly Road and Paw Paw Drive reopened Thursday, October 22 under a City of Holland traffic control order, [as reported by Ottawa News Network](https://www.ottawanewsnetwork.org/road-opened-eighth-street-holland/?ref=mosaicwestmichigan.com). BPW's project page calls the dates estimates that may change.  
Holland Board of Public Works · [source](https://www.hollandbpw.com/en/project-updates/460-8th-street-water-main-repair-project?ref=mosaicwestmichigan.com)

The [City of Holland's 2026 project pages](https://www.cityofholland.com/1319/2026-Construction-Projects?ref=mosaicwestmichigan.com) list nothing new this week: the Waverly Road resurfacing between Chicago Drive and 16th Street is tied to the BPW project, and the 2026 resurfacing list was milled and repaved by the end of August with pavement markings scheduled for September, per a page updated August 31\. The 40th Street reconstruction and Central Avenue and 7th Street traffic light pages were last updated in January and give no current status.

### Holland Township

- Closed**120th Avenue, Lakewood Boulevard to James Street**  
Sanitary sewer installation under a permit. The project list shows the closure as May 4 to November 15; Ottawa News Network's [October 26 construction update](https://www.ottawanewsnetwork.org/weekly-construction-update-oct-26/?ref=mosaicwestmichigan.com) listed an anticipated reopening of November 30.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Closed**James Street at 120th Avenue**  
Sanitary sewer work. Closed September 21 to November 30.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Closed**104th Avenue over Black Creek**  
Bridge replacement. Closed July 6 to November 30.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Reopened**Beeline Road and Greenly Street, Riley Street to 120th Avenue**  
The project list now marks this resurfacing job, which had lane closures since September 28, as completed.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)

The North 144th Avenue closure between Butternut Drive and Quincy Street, which the project list showed last Monday with an October 23 end date, is no longer on the list. The Road Commission's [notice](https://ottawacorc.com/road-closure-n-144th-ave-butternut-dr-to-quincy-st-holland-twp-begins-oct-12-2026/?ref=mosaicwestmichigan.com) is the last word posted on it.

### Olive and Port Sheldon townships, north of Holland

- Closed**112th Avenue, Port Sheldon Street to New Holland Street**  
Closed to through traffic since Thursday, October 29 for a City of Wyoming water transmission line, under a permit. The closure includes the 112th Avenue and Van Buren Street intersection. The project list shows October 29 to November 20; the Road Commission's [notice](https://ottawacorc.com/road-closure-112th-ave-port-sheldon-st-to-new-holland-st-olive-twp-begins-oct-29-2026/?ref=mosaicwestmichigan.com) says the work lasts through late November. The posted detour is New Holland Street to 120th Avenue to Port Sheldon Street. The Road Commission calls the dates tentative.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Closed**96th Avenue south of Stanton Street**  
Culvert replacement, closed to through traffic since Wednesday, October 28 and scheduled through Monday, November 2\. The posted detour is 96th Avenue to Fillmore Street to 76th Avenue to Taylor Street. The notice places the job in Olive and Blendon townships; the project list says Olive Township. The Road Commission calls the dates tentative.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-closure-96th-ave-s-of-stanton-st-olive-blendon-twps-begins-oct-28-2026/?ref=mosaicwestmichigan.com)
- Closed**Butternut Drive at Van Buren Street, Port Sheldon Township**  
The intersection is closed October 19 through November 13 for the City of Wyoming water transmission line, under a permit. The posted detour is Port Sheldon Street to 152nd Avenue to New Holland Street. The Road Commission calls the dates tentative.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-closure-butternut-dr-at-van-buren-st-port-sheldon-twp-begins-oct-19-2026/?ref=mosaicwestmichigan.com)
- Closed**Van Buren Street, Butternut Drive to US-31 and US-31 to 120th Avenue**  
Water main installation in two segments; a detour map is posted. Closed since fall 2025, through November 30.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Closed**164th Avenue, Butternut Drive to New Holland Street**  
Water transmission main. Closed August 10 to November 30.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)

## Zeeland

No county road closures are listed in Zeeland or Zeeland Township this week.

## Tri-Cities

### Grand Haven, Spring Lake and Ferrysburg

- Status unconfirmed**172nd Avenue, Comstock Street to Hayes Street, Grand Haven Township**  
Sanitary and storm sewer work under a permit, closed since October 12\. The project list still shows the road closed, with a scheduled end date of Friday, October 30; the Road Commission's [notice](https://ottawacorc.com/road-closure-172nd-ave-comstock-st-to-hayes-st-grand-haven-twp-begins-oct-12-2026/?ref=mosaicwestmichigan.com) said October 23\. Its current status could not be confirmed. The posted detour is Comstock Street to 168th Avenue to Hayes Street.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Lane closure**Taft Street, 174th Avenue to 168th Avenue, Spring Lake Township**  
Resurfacing and paved shoulders. The project list shows a lane closure since October 19 with no end date; the Road Commission's notice says the work runs through early November, with traffic open under temporary lane closures and flag control. Ottawa News Network's [October 26 construction update](https://www.ottawanewsnetwork.org/weekly-construction-update-oct-26/?ref=mosaicwestmichigan.com) listed an anticipated completion of October 30.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-resurfacing-taft-st-174th-ave-to-168th-ave-spring-lake-twp-begins-week-of-oct-19-2026/?ref=mosaicwestmichigan.com)

No MDOT lane closures on US-31 in the Tri-Cities were listed when Mi Drive was checked Sunday night.

## Hudsonville and Jenison

### Georgetown, Jamestown and Blendon townships

- Reopened**48th Avenue and Baldwin Street roundabout**  
The project list now marks the roundabout construction, which closed the intersection since July 27, as completed, with an end date of Saturday, October 24.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Reopened**48th Avenue, Port Sheldon Street to Baldwin Street**  
The project list now marks the water transmission main job, closed since March 30, as completed, with an end date of Saturday, October 24.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Status unconfirmed**96th Avenue north of Blair Street**  
Culvert replacement, closed since Tuesday, October 20\. The project list still shows the road closed, with a scheduled end date of Friday, October 23\. Its current status could not be confirmed. The posted detour is 96th Avenue to Port Sheldon Street to 88th Avenue to Tyler Street.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-closure-96th-ave-n-of-blair-st-olive-blendon-twp-begins-oct-20-2026/?ref=mosaicwestmichigan.com)
- Lane closure**12th Avenue, Port Sheldon Street to Baldwin Street**  
Mill and resurface with temporary lane closures under flag control. The project list still shows a lane closure with dates of October 5 to 30; the Road Commission's notice said the work runs into late October or early November, and Ottawa News Network's [October 26 construction update](https://www.ottawanewsnetwork.org/weekly-construction-update-oct-26/?ref=mosaicwestmichigan.com) listed an anticipated completion of November 15.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-resurfacing-12th-ave-baldwin-st-to-port-sheldon-st-georgetown-twp-begins-week-of-oct-12-2026/?ref=mosaicwestmichigan.com)
- Reopened**Baldwin Street, 20th Avenue to Cottonwood Drive**  
The project list now marks this mill and resurface job, which had lane closures since September 28, as completed.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Reopened**Baldwin Street, 56th Avenue to 48th Avenue, Blendon Township**  
The project list now marks this resurfacing job, scheduled for October 5 to 17, as completed.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)
- Reopened**New Holland Street, Chicago Drive to the Hudsonville city limits**  
The project list now marks this resurfacing and paved shoulders job, which had lane closures since October 5, as completed.  
Ottawa County Road Commission · [source](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com)

No MDOT lane closures on I-196 or M-6 near Hudsonville and Jenison were listed when Mi Drive was checked Sunday night.

## Allendale and Coopersville

### Allendale, Polkton and Crockery townships

- Lane closure**I-96 eastbound, 112th Avenue to 88th Avenue**  
Left lane closed since October 19, through November 14 at 5 p.m.  
MDOT Mi Drive · [source](https://mdotjboss.state.mi.us/MiDrive/map?ref=mosaicwestmichigan.com)
- Lane closure**I-96 westbound, 68th Avenue to 88th Avenue**  
Left lane closed since October 19, through November 14 at 5 p.m.  
MDOT Mi Drive · [source](https://mdotjboss.state.mi.us/MiDrive/map?ref=mosaicwestmichigan.com)

The 60th Avenue closure between Lincoln Street and Comfort Drive in Allendale Township, which the project list showed last Monday with an October 30 end date, is no longer on the list.

## Saugatuck, Douglas and Fennville

### I-196 and Allegan County roads

- Closed**Old Allegan Road at I-196**  
Closed in both directions between the I-196 ramps for the I-196 project. The Mi Drive records show July 13 to November 13 at 3 p.m.  
MDOT Mi Drive · [source](https://mdotjboss.state.mi.us/MiDrive/map?ref=mosaicwestmichigan.com)
- Lane closure**I-196 northbound, mile 38 to mile 39**  
Left lane closed through November 13.  
MDOT Mi Drive · [source](https://mdotjboss.state.mi.us/MiDrive/map?ref=mosaicwestmichigan.com)

Last week's I-196 traffic stoppages northbound between 124th Avenue and 68th Street and the southbound left-lane closure from Old Allegan Road to Wiley Road were no longer on the Mi Drive map when it was checked Sunday night.

The Allegan County Road Commission directs drivers to its Facebook page for road project and maintenance updates. Its [2026 project list](https://www.alleganroads.org/2026-projects--bids.html?ref=mosaicwestmichigan.com) includes a culvert replacement and sinkhole repair along the bike path at 62nd Street and Blue Star Highway in Laketown Township. Bids were opened September 16, and the [project specifications](https://www.alleganroads.org/uploads/4/8/8/5/488583/specifications.pdf?ref=mosaicwestmichigan.com) set a November 15 completion deadline. A start date and traffic restrictions were not identified in the records reviewed. The closed section of Lakeshore Drive in Saugatuck Township stays closed while the Road Commission pursues federal grant funding to reconnect it.

Compiled the night of Sunday, November 1 from the [Ottawa County Road Commission project list](https://ottawacorc.com/road-work-projects/?ref=mosaicwestmichigan.com) and [road work notices](https://ottawacorc.com/category/road-work-updates/?ref=mosaicwestmichigan.com), [MDOT Mi Drive](https://mdotjboss.state.mi.us/MiDrive/map?ref=mosaicwestmichigan.com) (individual construction records read Sunday night), the [Holland Board of Public Works](https://www.hollandbpw.com/en/project-updates/460-8th-street-water-main-repair-project?ref=mosaicwestmichigan.com), the [City of Holland](https://www.cityofholland.com/1319/2026-Construction-Projects?ref=mosaicwestmichigan.com) (and its traffic control order for 8th Street, [as reported by Ottawa News Network](https://www.ottawanewsnetwork.org/road-opened-eighth-street-holland/?ref=mosaicwestmichigan.com) on October 22) and the [Allegan County Road Commission](https://www.alleganroads.org/road-closures.html?ref=mosaicwestmichigan.com). Dates are the agencies' estimates and move with weather and contractors. Know about a closure we missed, including city streets in Zeeland, Grand Haven, Hudsonville, Coopersville, Saugatuck, Douglas or Fennville? [Tell us](https://www.mosaicwestmichigan.com/nominate/).